Construction remains on-budget and on schedule to be complete in late 2026, Dominion said, and the project is now 43% ...
Dominion Energy has installed 78 monopile and four offshore substation foundations for as part of the first offshore ...
There is almost 65 gigawatts of offshore wind capacity under development in the U.S., enough to power more than 26 million ...
Dominion Energy has successfully completed the first monopile installation season for its Coastal Virginia Offshore Wind ...
Dominion Energy has successfully completed its first monopile installation season for on-time and on-budget Coastal Virginia Offshore Wind.
Dominion Energy has installed 78 monopile foundations and four offshore substation foundations for the 2.6-gigawatt Coastal ...
Installation of more monopile foundations, staged at Portsmouth Marine Terminal, will resume in May, the company said.
the South Fork Wind Farm off Montauk Point on New York’s Long Island, and the Coastal Virginia Offshore Wind pilot project.