Dominion Energy has installed 78 monopile and four offshore substation foundations for as part of the first offshore ...
Construction remains on-budget and on schedule to be complete in late 2026, Dominion said, and the project is now 43% ...
said Tuesday it received the last two major federal approvals needed to begin construction of the Coastal Virginia Offshore Wind project, keeping the largest planned U.S. offshore wind farm on ...
Currently operating projects include the Block Island Wind Farm in Rhode Island, the Coastal Virginia Offshore Wind pilot ...
Dominion Energy has successfully completed its first monopile installation season for on-time and on-budget Coastal Virginia Offshore Wind.
In campaign appearances, the president-elect railed against offshore wind and promised to sign an executive order to block ...
Dominion Energy completes initial installation campaign for the Coastal Virginia Offshore Wind project, on track for ...
Installation of more monopile foundations, staged at Portsmouth Marine Terminal, will resume in May, the company said.
(AP) — A European company has canceled plans to build blades for offshore wind turbines in coastal Virginia ... Energy's enormous wind farm off the coast of Virginia Beach.
the Block Island Wind Farm (Sea2Shore Project) and the Coastal Virginia Offshore Wind Pilot Project. Graph generated using data from the BOEM. RODA also claims federal agencies failed to ...
the South Fork Wind Farm off Montauk Point on New York’s Long Island, and the Coastal Virginia Offshore Wind pilot project.
The 2.6-gigawatt Coastal Virginia Offshore Wind project is slated ... Construction of the offshore wind farm started in May. The company said nearly 1,000 Virginia workers, including more than ...